How do I order a Lead-Based Paint inspection for an FHA buyer?

W
Written by WILMOTH Group

For homes built prior to 1978, with owner occupants using FHA financing, a lead-based paint inspection may be requested. The steps involve ordering, performing lead-based paint testing, remediation if needed, and payment.

The process begins when a HUD contract, that indicates FHA financing will be used, is accepted and ratified by HUD. The Asset Manager will initiate a work order to the Field Sales Manager (FSM) to inspect for any lead-based paint. The FSM will use HUD’s contractor to perform the clearance test and recommend any remediation. For the FHA financed buyer only, HUD will handle the remediation and cost.
​

This all will occur before closing.